e|agenda.NET
Sarasota County Schools
THE SCHOOL BOARD OF SARASOTA COUNTY, FLORIDA Landings Administrative Complex 1980 Landings Blvd. 6:30 P. M.
January 16, 2007 Board Meeting
Agenda Item #20


Title
ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE ASHTON ELEMENTARY SCHOOL - BUILDING 1 REROOFING PROJECT

Description
The architect has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.  A copy of the final punch list is available for review at the Construction Services Department.

Recommendation
That the work performed by Jon F. Swift, Inc. for the Ashton Elementary School - Building #1 Reroofing project be accepted as substantially complete as of 11/9/2006.

Contact
LEMPE & COLLINS

Financial Impact

N/A




Attachment:  BAIenc1-16-07AshtonBldg1ReroofSC.pdf